BUILDERS STILL WORKING
They arrive 8 AM; and, will usually finish at around: 4 to 5 PM.
So, far they...
- errected scaffolding to hold up collapsed ceiling/knocked down toilet/bathroom wall above
- knocked down the kitchen/bathroom wall above...also, demolished the rotten wooden ceiling joists
- added new wooden ceiling joists/turned off water
- turned water back on/added floorboards to go on top of the joists so that now it's possible to walk inside of the kitchen
- errected bathroom/kitchen wooden frames.../a van came JMLWasteRemoval...and, took away most of of the waste stored outside of the front part of the house; and, also, the old cooker (no longer working)
So far to date, I've paid them the sum of £3,500.00; with £300.00 still left to be paid.
£500.00 was to errect scaffolding/knock down wall.
£3,000.00 is to do the rest: bathroom/toilet.
£300.00 I'm not too sure what that's about...I think, it might be to hire the skip to get rid of the rubbish/rubble.
In fact, there is still so much more work remaining to do; but, because it will cost thousands...and, I really can't afford that...; therefore, I think, it's just going to have to wait.